Although I have Part Cost of 1.79 on the Raw Material Tab of the Estimate.
[attachment=4]
When I go to the Estimate Cacl Tab the Ea$1 is different.
[attachment=5]
This is because you have entered extra parts and Extra % on the material tab.
[attachment=6]
The additional material is not added in to the each price until you have an actual quantity that you are going to build. While technically an additional Extra Part of 1 would double the cost, and the 10% would add 10% for a quantity of 1 it would be a little misleading to display this until you have an actual quantity to build.